XYZ Contractors failed to pay a subcontractor and the sub filed a construction lien. The project owner wants to release the lien by posting a bond. Under Michigan law, the bond amount must be what percentage of the lien amount?
Correct Answer
B) 150%
Michigan Construction Lien Act 497 requires a bond equal to 150% of the lien amount to discharge a construction lien from the property.
Why This Is the Correct Answer
Under Michigan Construction Lien Act (Act 497), a property owner can discharge a construction lien by posting a surety bond equal to 150% of the lien amount. The extra 50% above the lien amount covers potential legal costs and ensures the claimant's position is adequately protected even after the lien is released from the property.
Why the Other Options Are Wrong
Option A: 125%
125% is incorrect. While this percentage appears in some other states' lien statutes, Michigan Act 497 specifically requires 150% for a lien discharge bond.
Option C: 100%
100% is incorrect. Posting a bond equal to only the lien amount would not adequately protect the claimant against legal fees and interest that may accrue during litigation. Michigan requires the additional 50% cushion.
Option D: 110%
110% is incorrect. This percentage is not specified in Michigan's Construction Lien Act for bond discharge purposes. It may be confused with bond requirements in other contexts or other states.
Memory Technique
Think '150% = Lien Liberation Premium.' To free property from a lien, you pay a premium β 100% of the lien plus a 50% safety buffer (for legal costs). The extra 50% is the 'freedom fee' for releasing the lien from the property before court resolution.
More Michigan Questions
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
A contractor's employee is injured on a job site in Michigan. The contractor's workers' compensation insurance has a $500 deductible per claim. The total medical costs are $12,500 and lost wages are $3,200. What is the contractor's out-of-pocket cost for this claim?
What is the minimum general liability insurance coverage amount required for Michigan residential builders?
Under Michigan Act 299, what is the consequence for a contractor who performs work outside the scope of their license classification?
A contractor discovers that a subcontractor has filed a construction lien against their project. The general contractor believes the lien is invalid. What is the primary legal mechanism to challenge the lien in Michigan?
Under Michigan Act 299, what happens if a contractor continues to work without a valid license after it expires?
Which of the following best describes the 'pay when paid' clause limitation under Michigan law?
A project has total costs of $180,000 including $75,000 labor and $105,000 materials. With workers compensation at 7.8% of labor costs and general liability at 0.4% of total costs, what are the combined insurance costs?
A Michigan contractor is forming an LLC. What is the minimum general liability insurance coverage required for residential builders under Michigan law?
Under Michigan Act 299, a contractor's license must be renewed every:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor completes work on March 15th but doesn't file a construction lien until June 20th. The property owner received a Notice of Furnishing on March 10th. Is the lien valid under Michigan law?
Next Question
Under Michigan law, which business entity type provides the most personal liability protection for contractors?
