Who is typically responsible for preparing as-built drawings on a construction project?
Correct Answer
B) The individual trade contractors
Individual trade contractors are typically responsible for marking up drawings with field changes in their scope of work and providing as-built information to the general contractor, who then coordinates the compilation of complete as-built drawings.
Why This Is the Correct Answer
Individual trade contractors are responsible for preparing as-built drawings because they are the ones actually performing the work and making field changes. Each trade contractor has intimate knowledge of their specific scope and any deviations from the original plans. They mark up the drawings with actual field conditions, changes, and installations as they occur during construction. The general contractor then coordinates and compiles these individual trade markups into complete as-built drawings for the project.
Why the Other Options Are Wrong
Option A: The general contractor
The owner's representative oversees the project but does not have the technical expertise or detailed knowledge of actual field installations to prepare as-built drawings.
Option C: The owner's representative
While architects create the original design drawings, they are typically not on-site during construction to observe and document field changes and actual installation conditions that occur during the building process.
Option D: The architect
The general contractor coordinates and compiles the as-built drawings from information provided by trade contractors, but does not typically prepare the detailed markups themselves since they don't perform the actual trade work.
Memory Technique
Think 'Trade = True' - the trade contractors know the TRUE conditions of what was actually built in the field.
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding contractor responsibilities
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
