EstatePass
Contract AdminPermitseasy20% of exam part

Which type of Certificate of Occupancy is issued for a building that will be occupied before all work is completely finished?

Correct Answer

D) Temporary Certificate of Occupancy

A Temporary Certificate of Occupancy allows occupancy before all work is complete, typically with specific conditions and time limitations. This is common for phased projects or when minor non-critical work remains.

Answer Options
A
Conditional Certificate of Occupancy
B
Partial Certificate of Occupancy
C
Permanent Certificate of Occupancy
D
Temporary Certificate of Occupancy

Why This Is the Correct Answer

A Temporary Certificate of Occupancy (TCO) is specifically designed to allow building occupancy before all construction work is completely finished. It is issued when the building is safe for occupancy but minor, non-critical work remains to be completed. The TCO comes with specific conditions that must be met and has time limitations, typically requiring the remaining work to be completed within a specified timeframe. This allows projects to proceed with occupancy while final touches or non-essential systems are completed.

Why the Other Options Are Wrong

Option A: Conditional Certificate of Occupancy

While a Conditional Certificate of Occupancy may sound similar, this is not the standard terminology used in Florida building codes for allowing occupancy before work completion. The correct term is Temporary Certificate of Occupancy.

Option B: Partial Certificate of Occupancy

A Partial Certificate of Occupancy typically refers to allowing occupancy of completed portions of a building while other sections remain under construction, rather than allowing occupancy when work is simply incomplete throughout.

Option C: Permanent Certificate of Occupancy

A Permanent Certificate of Occupancy is issued only after ALL work is completely finished and the building fully complies with all codes and regulations. This would not be appropriate for a building where work is still incomplete.

Memory Technique

TCO = 'Temporarily Can Occupy' - use this acronym to remember that Temporary Certificate of Occupancy allows occupancy before completion.

Reference Hint

Florida Building Code, Chapter 1, Section 110 - Certificate of Occupancy provisions

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.