Which situation would most likely justify the highest contingency percentage in a construction estimate?
Correct Answer
A) Renovation of a historic building with unknown existing conditions
Historic building renovation with unknown existing conditions presents the highest risk and uncertainty, justifying the highest contingency percentage. Unknown conditions like structural issues, hazardous materials, or code compliance problems can significantly impact costs.
Why This Is the Correct Answer
Historic building renovation with unknown existing conditions presents the highest level of uncertainty and risk in construction projects. These projects often reveal unexpected structural problems, hazardous materials like asbestos or lead paint, outdated electrical and plumbing systems, and compliance issues with modern building codes. The unknown nature of these conditions makes accurate cost estimation extremely difficult, requiring contingency percentages typically ranging from 15-30% or even higher to account for unforeseen discoveries during construction.
Why the Other Options Are Wrong
Option B: Construction using prefabricated building components
Construction using prefabricated building components reduces uncertainty because components are manufactured under controlled conditions with known specifications and costs. The assembly process is standardized and predictable, requiring lower contingency percentages than traditional construction methods.
Option D: Repeat construction of a previously built design
Repeat construction of a previously built design has the lowest risk since all potential issues have been identified and resolved in the original project. Costs are well-established, construction methods are proven, and there are no design unknowns, requiring minimal contingency of 3-7%.
Memory Technique
Think 'HISTORIC = HIDDEN RISKS' - Historic buildings hide the most surprises, requiring the highest contingency protection
Reference Hint
Florida Building Code Chapter 1 - General Provisions, and construction estimating references covering contingency planning and risk assessment
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
