EstatePass
Contract AdminPreconstructioneasy27% of exam part

Which estimating method provides the highest level of accuracy for construction cost estimates?

Correct Answer

D) Detailed unit cost method

The detailed unit cost method provides the highest accuracy because it breaks down all work into individual components with specific quantities, labor hours, and material costs.

Answer Options
A
Square foot method
B
Parametric method
C
Assemblies method
D
Detailed unit cost method

Why This Is the Correct Answer

The detailed unit cost method provides the highest accuracy because it breaks down every aspect of construction into individual work items with specific quantities, labor hours, material costs, and equipment needs. This granular approach accounts for all project variables and allows for precise cost calculations based on actual field conditions. It requires the most time and effort but delivers estimates with accuracy levels of ±5-10%, making it ideal for final bidding and project execution.

Why the Other Options Are Wrong

Option A: Square foot method

The square foot method is a conceptual estimating technique that uses cost per square foot multipliers based on building type and provides only rough order-of-magnitude estimates with accuracy of ±25-50%, making it suitable for early planning but not detailed bidding.

Option B: Parametric method

The assemblies method (also called systems method) groups related components together but still lacks the granular detail of individual unit costs, providing moderate accuracy of ±15-25% which is better than square foot but less precise than detailed unit costing.

Option C: Assemblies method

The parametric method uses mathematical models and statistical relationships between cost and project variables, but relies on historical data that may not account for specific project conditions, resulting in lower accuracy than detailed unit cost analysis.

Memory Technique

Think 'DETAIL = ACCURATE' - the more detailed the breakdown (individual units), the more accurate the estimate becomes.

Reference Hint

Florida Building Construction Standards and Practices - Chapter on Cost Estimating Methods and Project Management sections

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.