Contract AdminContractsmedium40% of exam part

Which document would typically contain the specific scope of work, schedule, and payment terms between a general contractor and subcontractor?

Correct Answer

A) AIA A401

AIA A401 is the Standard Form of Agreement Between Contractor and Subcontractor, which contains the specific scope, schedule, payment terms, and other provisions governing the subcontract relationship.

Answer Options
A
AIA A401
B
AIA A101
C
AIA A201
D
Notice to Proceed

Why This Is the Correct Answer

AIA A401 is specifically designed as the Standard Form of Agreement Between Contractor and Subcontractor. This document establishes the contractual relationship between the general contractor and subcontractor, detailing the subcontractor's scope of work, project schedule requirements, payment terms, and performance obligations. It serves as the primary governing document for subcontract work and includes provisions for coordination with the prime contract.

Why the Other Options Are Wrong

Option C: AIA A201

Notice to Proceed is a formal notification document that authorizes the start of work but does not contain detailed scope, schedule, or payment terms - these are established in the contract agreement.

Option D: Notice to Proceed

AIA A201 is the General Conditions of the Contract for Construction, which provides standard terms and conditions but is not the agreement document itself that contains specific scope, schedule, and payment terms.

Memory Technique

Think 'A401 = Agreement FOR ONE subcontractor' - the '4' represents the fourth party relationship (after owner, architect, contractor comes subcontractor)

Reference Hint

Florida Building Code Chapter 1, Section 107 - Construction Documents and AIA Contract Documents reference guide

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.