During a rough-in inspection, the building inspector finds several code violations. What is the contractor's next required action?
Correct Answer
D) Correct the violations and request a re-inspection
When violations are found during any inspection, the contractor must correct all violations and request a re-inspection before proceeding to the next phase of construction. Work cannot continue until the inspection passes.
Why This Is the Correct Answer
Option B is correct because Florida Building Code requires that all violations found during inspections must be corrected before work can proceed to the next phase. The contractor cannot continue construction until the inspector approves the corrected work through a re-inspection. This ensures safety standards are met and prevents defective work from being concealed by subsequent construction phases. The inspection process is sequential and each phase must pass before moving forward.
Why the Other Options Are Wrong
Option A: Schedule the next inspection immediately
Appeals are only appropriate when there's a legitimate dispute about code interpretation, not when clear violations exist. Appeals also take time and don't allow work to continue, making this an inefficient first step.
Option B: Continue with the project and address violations at final inspection
Continuing work with unresolved violations violates building codes and can result in stop-work orders, fines, and potential safety hazards. Violations must be corrected immediately, not deferred to final inspection.
Option C: Appeal the inspector's decision to the building department
Scheduling the next inspection without correcting violations is premature and violates code requirements. The inspector will not approve the next phase until current violations are resolved.
Memory Technique
Use the acronym 'CFR' - Correct violations, Fix problems, Request re-inspection. Think 'Code of Federal Regulations' to remember the order.
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, Section on Inspections and Approvals
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor wants to build a warehouse in an area zoned for residential use. The local zoning board has agreed to allow the project. What type of approval has been granted?
Next Question
Which document would typically contain the specific scope of work, schedule, and payment terms between a general contractor and subcontractor?
