EstatePass
Contract AdminPermitshard20% of exam part

A contractor fails to call for a required inspection and covers the work. The building official discovers this during the next scheduled inspection. What enforcement action is most likely?

Correct Answer

B) Issue a notice of violation requiring exposure of the work

When required inspections are missed and work is improperly covered, building officials typically issue a notice of violation requiring the contractor to expose the work for proper inspection at the contractor's expense.

Answer Options
A
Allow the work to remain covered with additional documentation
B
Issue a notice of violation requiring exposure of the work
C
Revoke the building permit immediately
D
Issue a fine but allow work to continue

Why This Is the Correct Answer

When a contractor fails to call for a required inspection and covers work that should have been inspected, the building official must ensure the work complies with approved plans and code requirements. The only way to verify compliance is to expose the covered work for proper inspection. This is standard enforcement procedure across Florida jurisdictions, and the contractor bears the cost and responsibility for uncovering and re-covering the work after inspection.

Why the Other Options Are Wrong

Option A: Allow the work to remain covered with additional documentation

Simply issuing a fine without requiring exposure would leave potentially non-compliant work hidden and uninspected. This creates liability issues for the building department and compromises public safety, as the primary purpose of inspections is to verify code compliance, not generate revenue through fines.

Option C: Revoke the building permit immediately

Permit revocation is an extreme measure typically reserved for serious violations, abandonment, or repeated non-compliance. Missing an inspection and covering work, while serious, is usually addressed through corrective action (exposing the work) rather than permit revocation, which would halt the entire project.

Option D: Issue a fine but allow work to continue

Allowing work to remain covered without inspection would compromise building safety and code compliance verification. Building officials cannot approve work they cannot see, and additional documentation cannot substitute for visual inspection of structural, electrical, plumbing, or other critical building components that may be hidden.

Memory Technique

Think 'EXPOSE to INSPECT' - covered work without inspection must be exposed for proper verification, at the contractor's expense.

Reference Hint

Florida Building Code, Chapter 1 - Scope and Administration, Section 110 (Inspections) and local building department enforcement procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.