EstatePass
NASCLAProject Mgmteasy22% of exam part

Which document should be used to formally communicate a change in project scope to all stakeholders?

Correct Answer

B) Change order

A change order is the formal document that communicates approved changes in scope, time, or cost to all project stakeholders and becomes part of the contract.

Answer Options
A
Request for Information (RFI)
B
Change order
C
Meeting minutes
D
Daily field report

Why This Is the Correct Answer

A change order is the contractually recognized document that formally authorizes and communicates modifications to project scope, schedule, or cost. Once executed, it becomes part of the contract and binds all parties.

Why the Other Options Are Wrong

Option A: Request for Information (RFI)

A Request for Information (RFI) is used to ask questions and clarify ambiguities in contract documents β€” it does not authorize or communicate scope changes. Submitting an RFI about a change does not formally modify the contract.

Option C: Meeting minutes

Meeting minutes record discussions and action items from project meetings but have no contractual authority to modify scope. They may document that a change was discussed, but they cannot replace a signed change order.

Option D: Daily field report

A daily field report documents on-site activities, weather, manpower, and events for that day. It is a record-keeping tool, not a contract modification instrument.

Memory Technique

Think of a change order as a 'mini-contract amendment.' Any time the original scope changes, money changes, or time changes, a change order is the document that makes it official and binding on all parties.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.