Which document is required before a new commercial building can be legally occupied by tenants?
Correct Answer
D) Certificate of Occupancy
A Certificate of Occupancy (CO) is required before any new building can be legally occupied. This document certifies that the building has been constructed according to approved plans and meets all applicable codes.
Why This Is the Correct Answer
A Certificate of Occupancy (CO) is the final document that legally authorizes occupancy of a building. It certifies that the structure has been inspected and meets all applicable building codes, zoning requirements, and safety standards. Without a CO, it is illegal for tenants to occupy the building, regardless of construction completion. This document serves as official confirmation that the building is safe and suitable for its intended use.
Why the Other Options Are Wrong
Option B: Environmental clearance
A building permit is required to START construction, not to occupy the building. The permit authorizes the construction work but does not certify that the completed building is safe for occupancy.
Option C: Building permit
Zoning approval is required early in the development process to ensure the proposed use is allowed in that location. However, zoning approval alone does not certify that the completed building meets safety codes and is ready for occupancy.
Memory Technique
Think 'CO = Can Occupy' - you cannot legally occupy any building without a Certificate of Occupancy, just like you can't drive without a license.
Reference Hint
Florida Building Code, Chapter 1 - Scope and Administration, Section on Certificates of Occupancy
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
