EstatePass
Contract AdminPreconstructioneasy27% of exam part

Which cost estimating method would be most appropriate for preliminary budgeting of a proposed office building when only basic square footage and building type are known?

Correct Answer

D) Square foot estimating method

Square foot estimating is ideal for early project phases when detailed information isn't available, using historical cost data per square foot for similar building types.

Answer Options
A
Assemblies estimating method
B
Detailed unit price method
C
Material takeoff method
D
Square foot estimating method

Why This Is the Correct Answer

Square foot estimating is the most appropriate method for preliminary budgeting when only basic information like square footage and building type are available. This method uses historical cost data from similar projects to calculate cost per square foot, then multiplies by the proposed building's square footage. It provides a reasonable budget estimate quickly without requiring detailed plans, specifications, or material quantities. This approach is specifically designed for early project phases when detailed design information hasn't been developed yet.

Why the Other Options Are Wrong

Option B: Detailed unit price method

Material takeoff method requires detailed construction drawings and specifications to quantify specific materials needed. This level of detail is not available when only basic square footage and building type are known for preliminary budgeting.

Option C: Material takeoff method

The assemblies estimating method requires knowledge of building systems and components (like foundation systems, wall assemblies, roofing systems) which goes beyond the basic square footage and building type information available during preliminary budgeting.

Memory Technique

Think 'SQUARE footage = SQUARE foot method' - when you only know the square footage, use square foot estimating!

Reference Hint

Look up cost estimating methods in the project management or estimating chapter of your contractor reference manual, typically found under 'Types of Construction Estimates' or 'Estimating Methods'.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.