A commercial project requires a zoning variance for building height. The current zoning allows 35 feet maximum, but the project requires 42 feet. What is the first step in the variance process?

Correct Answer

A) File a formal variance application with the zoning board

A formal variance application must be filed with the appropriate zoning board or planning commission before any permits can be issued. The variance process includes public hearings and must be approved before construction begins.

Answer Options
A
File a formal variance application with the zoning board
B
Contact neighboring property owners for approval
C
Submit building permit application with variance request
D
Begin construction and request variance during inspection

Why This Is the Correct Answer

Filing a formal variance application with the zoning board is the mandatory first step in the variance process. This application initiates the legal procedure that includes public notification, hearings, and official review. The zoning board must approve the variance before any building permits can be issued or construction can begin. This formal process ensures compliance with local zoning ordinances and due process requirements.

Why the Other Options Are Wrong

Option C: Submit building permit application with variance request

Beginning construction without proper approvals is illegal and can result in stop-work orders, fines, and potential demolition requirements. All variances must be approved before construction begins.

Option D: Begin construction and request variance during inspection

While neighbor notification may be part of the formal variance process, it is not the first step and is typically handled by the zoning board as part of their public hearing requirements, not by the applicant directly.

Memory Technique

Think 'V before P' - Variance before Permits. Just like you need permission before you can break a rule, you need variance approval before you can exceed zoning limits.

Reference Hint

Florida Building Code Chapter 1, Section 105 - Permits; Local zoning ordinance sections on variance procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.