EstatePass
Contract AdminPreconstructionmedium27% of exam part

Which cost estimating method would be most appropriate for a preliminary budget estimate during the design development phase?

Correct Answer

A) Square foot method

The square foot method is ideal for preliminary estimates when detailed drawings are not available. It provides quick, reasonably accurate cost estimates based on building area and type.

Answer Options
A
Square foot method
B
Historical cost method
C
Assemblies method
D
Detailed unit cost method

Why This Is the Correct Answer

The square foot method is most appropriate for preliminary budget estimates during design development because it provides quick, reasonably accurate cost estimates when detailed drawings and specifications are not yet available. This method uses cost per square foot based on building type and can be calculated with minimal information. It strikes the right balance between speed and accuracy needed during early design phases when major design decisions are still being made.

Why the Other Options Are Wrong

Option B: Historical cost method

The assemblies method requires more detailed information about building systems and components than is typically available during early design development, making it more suitable for later design phases.

Option D: Detailed unit cost method

The detailed unit cost method requires complete drawings, specifications, and material takeoffs to calculate costs for individual components, making it too detailed and time-consuming for preliminary estimates during design development.

Memory Technique

Think 'Square foot = Quick start' - both have similar sounds and the square foot method gives you a quick start on preliminary estimates

Reference Hint

Look up cost estimating methods in the project management or estimating chapter of your contractor reference manual

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.