Which cost estimating method would be most appropriate for a contractor preparing a preliminary budget estimate for a client during the design development phase?
Correct Answer
D) Assemblies method
During design development, the assemblies method is most appropriate as it provides better accuracy than square foot estimates while not requiring the complete detail needed for quantity takeoffs, which aren't possible without final drawings.
Why This Is the Correct Answer
The assemblies method is ideal for design development phase because it estimates costs using building systems and components (foundations, framing, roofing assemblies) rather than individual materials. This provides reasonable accuracy when architectural drawings show general building systems but lack the detailed specifications needed for precise quantity takeoffs. It balances accuracy with the level of design information available during this intermediate phase.
Why the Other Options Are Wrong
Option A: Detailed quantity takeoff method
Detailed quantity takeoff requires complete construction documents with specific materials, dimensions, and specifications. During design development, drawings lack sufficient detail for accurate material quantities, making this method premature and potentially inaccurate for preliminary budgeting purposes.
Option B: Unit price method
Unit price method requires knowing specific quantities of work items to multiply by unit costs. Since design development drawings don't provide detailed quantities of individual work items, this method cannot be effectively applied at this early design stage.
Option C: Square foot method
Square foot method is too crude for design development phase. While quick, it doesn't account for the building systems and complexity details that are emerging during design development, potentially leading to significant cost variations and inadequate budgeting accuracy.
Memory Technique
Remember 'ASSEMBLIES = ALMOST READY' - during design development, you can see building assemblies/systems but aren't ready for detailed takeoffs yet.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
