Which contract document would typically contain the specific scope of work, contract price, and completion date for a construction project?
Correct Answer
D) Owner-Contractor Agreement (A101)
The Owner-Contractor Agreement (A101) contains the basic commercial terms including scope, price, and schedule, while A201 contains the general administrative and legal conditions.
Why This Is the Correct Answer
The AIA A101 Owner-Contractor Agreement is the primary commercial document that identifies the project-specific terms: the scope of work, contract sum (price), and the contract time (completion date). It is the 'deal sheet' that captures the negotiated particulars of each unique project.
Why the Other Options Are Wrong
Option A: Technical Specifications
Technical Specifications (Division 1β33 of the spec book) describe materials, methods, and quality standards for specific work types. They do not contain contract price or completion dates β those are commercial terms, not technical ones.
Option B: Supplementary Conditions
Supplementary Conditions modify or supplement the General Conditions (A201) for project-specific legal or administrative requirements. They adjust standard clauses but do not contain the contract price or the overall scope narrative.
Option C: General Conditions (A201)
General Conditions (A201) contain the legal and administrative framework governing the relationship between parties β roles, rights, dispute resolution, changes, payments process. They are standardized across projects and intentionally do not contain project-specific commercial terms like price or schedule.
Memory Technique
A101 = 'The Deal' (Price, Scope, Schedule). A201 = 'The Rules' (How disputes are resolved, who does what). Think: you sign A101 first to make the deal, then A201 governs how you execute it.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A concrete slab requires 450 cubic yards of concrete with a water-cement ratio of 0.45. If each bag of cement weighs 94 pounds and the cement content is 564 pounds per cubic yard, how many bags of cement are needed?
Next Question
What is the primary purpose of a performance bond on a construction project?
