When evaluating subcontractor bids, a general contractor notices one bid is significantly lower than others. What is the most appropriate first step?
Correct Answer
C) Contact the subcontractor to verify the bid and scope understanding
The contractor should verify that the low bidder understands the scope and that the bid is legitimate before making any decisions, as significant discrepancies often indicate scope misunderstandings.
Why This Is the Correct Answer
Contacting the subcontractor to verify the bid and scope understanding is the most prudent first step when encountering a significantly low bid. This approach allows the general contractor to confirm that the subcontractor fully understands the project requirements and hasn't made calculation errors or omitted key scope items. It protects both parties from potential disputes and ensures the bid is based on accurate information. This verification process is a standard industry practice that demonstrates due diligence and professional responsibility.
Why the Other Options Are Wrong
Option A: Use the low bid to negotiate with other subcontractors
Rejecting the bid outright without investigation is premature and could result in losing a legitimate competitive advantage. The low bid might be valid due to the subcontractor's efficiency, lower overhead, or strategic pricing, so verification is necessary before making any decision.
Option B: Reject the bid as it's likely a mistake
Using the low bid to negotiate with other subcontractors without first verifying its legitimacy is unethical and potentially problematic. If the low bid is based on errors or scope misunderstanding, using it as a negotiation tool could damage relationships with other qualified subcontractors.
Memory Technique
Use the acronym 'VERIFY' - Very Extreme Rates Indicate Further Inquiry
Reference Hint
Florida Building Construction Standards - Chapter on Subcontractor Management and Bid Evaluation Procedures
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
