EstatePass
Contract AdminPreconstructioneasy27% of exam part

When estimating roofing materials, a contractor calculates 2,400 square feet of roof area. Using a 10% waste factor, how many squares of shingles are needed?

Correct Answer

A) 27 squares

Roof area with waste = 2,400 × 1.10 = 2,640 sq ft. Since one square = 100 sq ft, 2,640 ÷ 100 = 26.4 squares. Rounding up to the next whole square for ordering purposes gives 27 squares.

Answer Options
A
27 squares
B
24 squares
C
26.4 squares
D
26 squares

Why This Is the Correct Answer

Option D is correct because when calculating roofing materials, you must first add the waste factor (2,400 × 1.10 = 2,640 sq ft), then convert to squares by dividing by 100 (2,640 ÷ 100 = 26.4 squares). Since you cannot order partial squares of shingles, you must round up to the next whole number, which is 27 squares. This ensures adequate material coverage for the project.

Why the Other Options Are Wrong

Option C: 26.4 squares

Option C provides the mathematically correct calculation (26.4 squares) but fails to account for the practical reality that shingles are sold in whole squares only, requiring rounding up for ordering purposes.

Option D: 26 squares

Option A fails to include the 10% waste factor and simply converts the base roof area to squares (2,400 ÷ 100 = 24), which would result in insufficient materials for the job.

Memory Technique

Remember 'WAR': Waste factor first, Area calculation second, Round UP third - because you can't buy partial squares and running short is worse than having extra.

Reference Hint

Look up roofing material calculations and waste factors in the estimating chapter of your contractor reference manual, typically found under 'Material Takeoffs' or 'Roofing Systems'.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.