When encountering liquefiable soils during site preparation, which foundation approach does CBC typically require?
Correct Answer
B) Install deep foundations to stable soil
CBC requires deep foundations (piles or caissons) extending through liquefiable layers to reach stable, non-liquefiable soil or rock for adequate seismic performance.
Why This Is the Correct Answer
CBC requires that foundations on liquefiable soils extend through the liquefiable layer to reach stable, non-liquefiable soil or rock via deep foundation elements such as driven piles or drilled caissons. During an earthquake, liquefiable soils lose bearing capacity entirely, so any foundation element relying on them for support will fail. Deep foundations bypass the problem zone.
Why the Other Options Are Wrong
Option A: Increase footing width by 50%
Increasing footing width by 50% addresses bearing capacity under static loads but does nothing to solve liquefaction. Wider footings still sit in or above the liquefiable layer and will lose support during seismic shaking.
Option C: Apply soil stabilization chemicals
Soil stabilization chemicals (such as grouting or permeation) can be used in some cases, but CBC does not identify chemical stabilization as the primary or typical required approach. The code-preferred solution is bypassing the layer with deep foundations.
Option D: Use post-tensioned slabs exclusively
Mat (raft) foundations spread load across a large area but remain at or near the surface. They cannot transfer load below the liquefiable zone and will settle or tilt catastrophically if the soil liquefies beneath them.
Memory Technique
Liquefiable soil = 'quicksand' β you need to reach solid ground beneath it. Deep piles or caissons punch through the quicksand to the stable layer below. Go DEEP to get past the liquid.
More California Questions
A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?
You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?
According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?
A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?
You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?
A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?
During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?
During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?
What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?
You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During construction, you discover that the actual soil conditions differ significantly from those described in the geotechnical report. What is the appropriate next step?
Next Question
In Seismic Design Category E, what is the minimum lap splice length required for #5 reinforcing bars in a concrete shear wall?