When can a Temporary Certificate of Occupancy be issued for a new building?
Correct Answer
C) When the building is substantially complete and safe for intended use
A Temporary Certificate of Occupancy can be issued when the building is substantially complete and safe for its intended use, even if minor items remain unfinished. This allows occupancy while final details are completed.
Why This Is the Correct Answer
A Temporary Certificate of Occupancy (TCO) is issued when a building is substantially complete and safe for its intended use, even if minor finishing work remains. The key criteria are substantial completion and safety for occupancy, not a specific percentage of completion or all inspections being done. This allows property owners to begin using the building while contractors complete final details like landscaping, minor finishes, or punch list items.
Why the Other Options Are Wrong
Option A: When the contractor requests it in writing
A specific percentage like 75% is not the determining factor for a TCO. The building could be 90% complete but still unsafe for occupancy, or 70% complete but substantially safe for use. The focus is on functional safety and substantial completion, not an arbitrary percentage.
Option D: When 75% of construction is complete
A TCO can be issued even when some inspections remain incomplete, as long as the building is substantially complete and safe. The final inspection specifically may not be complete since minor work often remains, but critical safety systems must be functional and inspected.
Memory Technique
TCO = 'Two Criteria Only' - Substantially complete + Safe for use
Reference Hint
Florida Building Code, Chapter 1, Section 110 - Certificate of Occupancy provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
