EstatePass
NASCLAContractsmedium15% of exam part

When a subcontractor's work damages another subcontractor's completed work, who is typically responsible for the repair costs under standard subcontract terms?

Correct Answer

C) The subcontractor who caused the damage

Under standard subcontract terms, each subcontractor is typically responsible for damage they cause to other subcontractors' work, including repair costs and schedule impacts.

Answer Options
A
The damaged subcontractor's insurance
B
The owner
C
The subcontractor who caused the damage
D
The general contractor

Why This Is the Correct Answer

Under standard subcontract agreements (and consistent with AIA and industry-standard terms), each subcontractor bears responsibility for damage they cause to work performed by others on the same project. The subcontractor whose work caused the damage is liable for the repair costs and any resulting schedule impacts. This principle of individual accountability is built into most standard subcontract indemnification and damage clauses.

Why the Other Options Are Wrong

Option A: The damaged subcontractor's insurance

The damaged subcontractor's insurance is not the first-line responsible party. While the damaged sub's insurer might pay out in some scenarios, the insurer would then subrogate against the at-fault subcontractor. Insurance is not a shield for the causing party's negligence under standard contract terms.

Option B: The owner

The owner is generally not responsible for damages caused by one subcontractor to another's work. The owner contracts with the general contractor, who is responsible for coordinating subcontractors. Inter-subcontractor damage is typically handled within the GC's scope of project management.

Option D: The general contractor

While the general contractor has overall project responsibility, the standard subcontract terms place the financial burden of repair on the specific subcontractor who caused the damage. The GC may facilitate resolution, but the causing sub is typically required to repair or bear the cost under the indemnification provisions of their subcontract.

Memory Technique

Remember 'You break it, you buy it' β€” the subcontractor who caused the damage pays for the damage. This is the same principle as general tort liability applied to the construction site. The causing party's own subcontract indemnity clause obligates them to repair or compensate for damage they caused.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.