When a subcontractor's work damages another subcontractor's completed work, who is typically responsible for the repair costs under standard subcontract terms?
Correct Answer
C) The subcontractor who caused the damage
Under standard subcontract terms, each subcontractor is typically responsible for damage they cause to other subcontractors' work, including repair costs and schedule impacts.
Why This Is the Correct Answer
Under standard subcontract agreements (and consistent with AIA and industry-standard terms), each subcontractor bears responsibility for damage they cause to work performed by others on the same project. The subcontractor whose work caused the damage is liable for the repair costs and any resulting schedule impacts. This principle of individual accountability is built into most standard subcontract indemnification and damage clauses.
Why the Other Options Are Wrong
Option A: The damaged subcontractor's insurance
The damaged subcontractor's insurance is not the first-line responsible party. While the damaged sub's insurer might pay out in some scenarios, the insurer would then subrogate against the at-fault subcontractor. Insurance is not a shield for the causing party's negligence under standard contract terms.
Option B: The owner
The owner is generally not responsible for damages caused by one subcontractor to another's work. The owner contracts with the general contractor, who is responsible for coordinating subcontractors. Inter-subcontractor damage is typically handled within the GC's scope of project management.
Option D: The general contractor
While the general contractor has overall project responsibility, the standard subcontract terms place the financial burden of repair on the specific subcontractor who caused the damage. The GC may facilitate resolution, but the causing sub is typically required to repair or bear the cost under the indemnification provisions of their subcontract.
Memory Technique
Remember 'You break it, you buy it' β the subcontractor who caused the damage pays for the damage. This is the same principle as general tort liability applied to the construction site. The causing party's own subcontract indemnity clause obligates them to repair or compensate for damage they caused.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
