What is the primary purpose of the strong-motion instrumentation requirements in the CBC for certain buildings?

Correct Answer

B) To record seismic response data for future code development

Strong-motion instrumentation is required to collect data on how buildings respond to seismic events, which helps improve future seismic design codes and standards.

Answer Options
A
To automatically shut off utilities during earthquakes
B
To record seismic response data for future code development
C
To alert emergency services of structural damage
D
To monitor building occupancy levels

Why This Is the Correct Answer

Strong-motion instruments (accelerometers) record actual ground and structural acceleration data during seismic events. This data is collected and analyzed by engineers and researchers to understand how buildings actually behave during earthquakes, which directly informs improvements to future seismic design codes and standards.

Why the Other Options Are Wrong

Option A: To automatically shut off utilities during earthquakes

Automatically shutting off utilities during earthquakes is the function of seismic gas shutoff valves (required separately under California law), not strong-motion instruments. Strong-motion instruments are passive recording devices, not active control systems.

Option C: To alert emergency services of structural damage

Alerting emergency services of structural damage is the role of post-earthquake inspection programs and occupant reporting, not strong-motion instruments. These instruments record data but do not transmit real-time damage alerts.

Option D: To monitor building occupancy levels

Monitoring building occupancy levels is entirely unrelated to strong-motion instrumentation. Occupancy monitoring uses separate systems such as access control or occupancy sensors.

Memory Technique

Think of strong-motion instruments as 'earthquake cameras' β€” they record what happens so engineers can learn and improve codes. They don't act during the earthquake; they just record it for future study.

Was this explanation helpful?

More California Questions

A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?

You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?

According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?

A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?

You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?

A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?

During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?

During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?

What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?

You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.