What is the primary purpose of including contingency in a construction estimate?
Correct Answer
A) To cover unforeseen conditions and minor scope changes
Contingency is specifically included to cover unforeseen conditions, minor changes, and uncertainties that may arise during construction. It serves as a buffer for unexpected costs that are within the general scope of work.
Why This Is the Correct Answer
Contingency is a standard construction estimating practice that provides a financial buffer for unexpected conditions that fall within the project's general scope. It covers items like unforeseen site conditions, minor design clarifications, small scope adjustments, and other uncertainties that cannot be precisely predicted during the estimating phase. This buffer helps ensure project completion without major budget overruns while maintaining the contractor's ability to handle normal construction variables.
Why the Other Options Are Wrong
Option B: To cover material price escalation over multiple years
Material price escalation over multiple years is a long-term economic factor that should be addressed through escalation clauses in contracts or specific price adjustment provisions, not through contingency. Contingency is for short-term, project-specific unknowns, not broad market fluctuations.
Option D: To pay for permit fees
Permit fees are known, predictable costs that should be included as specific line items in the estimate. Contingency is not meant to cover identifiable, calculable expenses like permits, but rather unexpected conditions that cannot be predetermined.
Memory Technique
Think 'Contingency = Construction Cushion' - it's a cushion for unexpected bumps in the road, not a pillow to make profits more comfortable.
Reference Hint
Look up construction estimating principles in Chapter 9 of the Florida Building Code or construction management references covering project cost estimating and contingency planning.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which type of bond guarantees that the contractor will pay all subcontractors, suppliers, and laborers?
Next Question
A 15,000 square foot office building is being estimated using the square foot method. Comparable projects cost between $185 and $210 per square foot. What is the estimated cost range?
