What is the primary difference between a unit price contract and a lump sum contract?
Correct Answer
B) Unit price contracts pay based on actual quantities installed, lump sum contracts pay a fixed amount
Unit price contracts pay based on actual quantities of work performed at predetermined unit rates, while lump sum contracts pay a fixed total amount regardless of actual quantities.
Why This Is the Correct Answer
Option B correctly identifies the fundamental difference between these contract types. Unit price contracts establish predetermined rates for specific units of work (per square foot, per cubic yard, etc.) and payment is calculated by multiplying these rates by the actual quantities installed. Lump sum contracts establish a fixed total price for the entire project scope, regardless of the actual quantities of materials or labor required. This distinction is crucial for contractors to understand risk allocation and payment structures.
Why the Other Options Are Wrong
Option A: Unit price contracts have shorter payment terms than lump sum contracts
Performance bond requirements are determined by project specifications, contract value, and owner requirements, not by the contract pricing method. Both unit price and lump sum contracts may or may not require performance bonds depending on these factors.
Option D: Unit price contracts require performance bonds, lump sum contracts do not
Payment terms (such as monthly progress payments, net 30 days, etc.) are negotiated contract provisions that are independent of whether the contract uses unit pricing or lump sum pricing. Both contract types can have identical payment schedules.
Memory Technique
Think 'Unit = Actual' (you get paid for actual units installed) vs 'Lump = Locked' (payment amount is locked in regardless of quantities)
Reference Hint
Construction Contracting chapter on Contract Types and Pricing Methods
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During contract closeout, the architect issues a Certificate of Substantial Completion. A subcontractor discovers a defect in their work 8 months later. The owner demands the general contractor fix the defect immediately. What is the contractor's best course of action?
Next Question
Under Chapter 489, F.S., what is required for a contractor to perform work outside their classification?
