What is the primary difference between a unit price contract and a lump sum contract?

Correct Answer

B) Unit price contracts pay based on actual quantities installed, lump sum contracts pay a fixed amount

Unit price contracts pay based on actual quantities of work performed at predetermined unit rates, while lump sum contracts pay a fixed total amount regardless of actual quantities.

Answer Options
A
Unit price contracts have shorter payment terms than lump sum contracts
B
Unit price contracts pay based on actual quantities installed, lump sum contracts pay a fixed amount
C
Unit price contracts include material costs, lump sum contracts do not
D
Unit price contracts require performance bonds, lump sum contracts do not

Why This Is the Correct Answer

Option B correctly identifies the fundamental difference between these contract types. Unit price contracts establish predetermined rates for specific units of work (per square foot, per cubic yard, etc.) and payment is calculated by multiplying these rates by the actual quantities installed. Lump sum contracts establish a fixed total price for the entire project scope, regardless of the actual quantities of materials or labor required. This distinction is crucial for contractors to understand risk allocation and payment structures.

Why the Other Options Are Wrong

Option A: Unit price contracts have shorter payment terms than lump sum contracts

Performance bond requirements are determined by project specifications, contract value, and owner requirements, not by the contract pricing method. Both unit price and lump sum contracts may or may not require performance bonds depending on these factors.

Option D: Unit price contracts require performance bonds, lump sum contracts do not

Payment terms (such as monthly progress payments, net 30 days, etc.) are negotiated contract provisions that are independent of whether the contract uses unit pricing or lump sum pricing. Both contract types can have identical payment schedules.

Memory Technique

Think 'Unit = Actual' (you get paid for actual units installed) vs 'Lump = Locked' (payment amount is locked in regardless of quantities)

Reference Hint

Construction Contracting chapter on Contract Types and Pricing Methods

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.