What is the primary difference between a contingency and an allowance in construction estimating?
Correct Answer
A) Contingencies cover unknown risks, allowances cover known but unspecified items
Contingencies address unknown risks and unforeseen conditions, while allowances are specific budget amounts for known items that haven't been selected yet, such as fixtures or finishes.
Why This Is the Correct Answer
Option B correctly identifies the fundamental distinction between contingencies and allowances in construction estimating. Contingencies are budget reserves set aside to handle unexpected problems, unforeseen site conditions, or unknown risks that may arise during construction. Allowances, on the other hand, are predetermined budget amounts allocated for specific items that are known to be needed but haven't been selected or specified yet, such as plumbing fixtures, light fixtures, or flooring materials. This distinction is crucial for proper project budgeting and cost control.
Why the Other Options Are Wrong
Option C: Contingencies are paid to the owner, allowances are kept by the contractor
This is incorrect because neither contingencies nor allowances are specifically required by law. Both are estimating tools used at the discretion of the contractor or as negotiated in the contract. Their use depends on project complexity, contract type, and risk assessment rather than legal requirements.
Option D: Contingencies are always a percentage, allowances are fixed amounts
This is incorrect because both contingencies and allowances are typically included in the contract price and paid by the owner as part of the total project cost. Neither is specifically 'kept' by the contractor - they are budget line items that serve different purposes in the overall estimate.
Memory Technique
Think 'C for Contingency = Curveballs (unexpected)' and 'A for Allowance = Anticipated but not Assigned (known items not yet selected)'
Reference Hint
Look up construction estimating principles in Chapter 9 of the Florida Building Code or estimating reference materials covering project cost development and risk management.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor is evaluating whether to purchase a $85,000 excavator or rent it for $3,500 per month. The excavator will be needed for 18 months and has an expected resale value of $55,000. Which option is more economical?
Next Question
During construction, you discover that the structural steel inspection was failed due to improper welding. What is the required next step before proceeding with work?
