What is the maximum monetary limit for a Registered General Contractor in Florida?
Correct Answer
B) $200,000 per contract and $600,000 aggregate
Florida Statute Chapter 489 establishes that Registered General Contractors are limited to $200,000 per individual contract with an aggregate limit of $600,000 for all outstanding contracts at any given time.
Why This Is the Correct Answer
Option A is correct because Florida Statute Chapter 489 specifically establishes monetary limitations for Registered General Contractors at $200,000 per individual contract and $600,000 aggregate for all outstanding contracts. These limits distinguish Registered General Contractors from Certified General Contractors, who have no monetary limitations. The aggregate limit ensures contractors don't exceed their bonding and financial capacity across multiple simultaneous projects.
Why the Other Options Are Wrong
Option A: $500,000 per contract and $1,500,000 aggregate
Option C presents significantly higher limits that exceed what is permitted for Registered General Contractors under Florida law. The $500,000 per contract and $1,500,000 aggregate amounts might be confused with limits for other contractor classifications or represent outdated information. These figures do not align with the current statutory requirements in Chapter 489.
Option C: No monetary limitation
Option D is incorrect because Florida Statute Chapter 489 explicitly establishes monetary limitations for Registered General Contractors. While Certified General Contractors may have no monetary limitations in some cases, Registered General Contractors are specifically restricted by law. This option might confuse candidates who mix up the different contractor license classifications and their respective limitations.
Option D: $300,000 per contract and $900,000 aggregate
Option B incorrectly states higher monetary limits than what Florida law actually establishes. The $300,000 per contract and $900,000 aggregate figures do not correspond to any recognized contractor classification in Florida Statute Chapter 489. These amounts may confuse candidates who might think of different state requirements or misremember the actual statutory limits for Registered General Contractors.
Memory Technique
Remember '2-6 Rule': Registered contractors are limited to $200,000 per contract (starts with 2) and $600,000 aggregate (starts with 6). Think 'Registered = Restricted' to remember they have limits.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
