Under Title 24, a new home's HVAC system must meet specific duct sealing requirements. What is the maximum allowable duct leakage rate for new construction?
Correct Answer
B) 6% of fan flow
Title 24 requires duct systems in new construction to have leakage rates not exceeding 6% of fan flow when tested at 25 Pascals, ensuring energy efficiency.
Why This Is the Correct Answer
Title 24 Part 6 (California Energy Code) sets the maximum allowable duct leakage at 6% of fan flow when tested at 25 Pascals for new construction. This threshold balances practical installation tolerances with meaningful energy savings — tighter duct systems reduce conditioned-air losses that inflate heating and cooling bills.
Why the Other Options Are Wrong
Option A: 10% of fan flow
10% of fan flow is too lenient and does not meet Title 24 new-construction standards. It may be confused with older or less stringent standards, but California's energy code demands tighter sealing to meet its aggressive efficiency goals.
Option C: 12% of fan flow
12% of fan flow far exceeds the allowable limit. Leakage at this level would represent a significant energy waste and would fail a Title 24 duct leakage test, triggering mandatory remediation before a certificate of occupancy is issued.
Option D: 8% of fan flow
8% of fan flow is closer to the correct answer but still exceeds the 6% maximum. Candidates who recall a number near 6% but are unsure of the exact figure sometimes guess 8%, making this a common distractor.
Memory Technique
Think '6 for new' — a brand-new duct system should be nearly airtight, and 6% is the strictest common threshold. Picture a brand-new sealed envelope: only 6 out of 100 letters leak out.
More California Questions
A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?
You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?
According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?
A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?
You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?
A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?
During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?
During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?
What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?
You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?