Under Nevada lien law, what is the maximum amount a materialman can claim in a mechanics' lien if they supplied $45,000 in materials but the total contract amount was $40,000?
Correct Answer
A) $40,000
Under NRS 108, a mechanics' lien cannot exceed the contract amount between the owner and the original contractor, regardless of the value of materials supplied. The lien is limited to $40,000.
Why This Is the Correct Answer
Under NRS 108, a mechanics' lien cannot exceed the contract amount between the owner and the original contractor. Even though the materialman supplied $45,000 worth of materials, the lien is capped at the $40,000 contract amount. This prevents the total of all liens from exceeding the owner's contractual obligation.
Why the Other Options Are Wrong
Option B: $42,500
$42,500 represents the average of the two amounts and has no legal basis under Nevada lien law. There is no statutory provision for averaging the materials cost and contract amount to determine lien limits.
Option C: $45,000
$45,000 reflects the actual value of materials supplied but exceeds the legal cap. Nevada lien law protects the owner by ensuring liens cannot collectively exceed what the owner agreed to pay under the contract. A materialman cannot recover more than the owner's total contractual exposure.
Option D: $85,000
$85,000 (the sum of both amounts) has no basis in Nevada lien law. Lien amounts are capped at the contract price β they cannot exceed the owner's agreement, let alone double it.
Memory Technique
The owner's contract price is the ceiling for all mechanics' liens. Think of it as a pie: the contract amount ($40,000) is the whole pie. No single slice (lien) can be larger than the whole pie, no matter how much material was delivered.
More nv-supplement Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
