Under Michigan's Construction Lien Act 497, what is the maximum time period to file a construction lien after the last day of work performed?

Correct Answer

B) 90 days

Michigan's Construction Lien Act 497 requires construction liens to be filed within 90 days after the last day of work performed on the project.

Answer Options
A
60 days
B
90 days
C
180 days
D
120 days

Why This Is the Correct Answer

The correct answer is B (90 days). Michigan's Construction Lien Act 497 establishes a 90-day deadline from the contractor's last day of work on the project to record a construction lien with the county register of deeds. Missing this deadline results in the loss of lien rights.

Why the Other Options Are Wrong

Option A: 60 days

60 days is incorrect. While 60 days is a common lien deadline in some other states, Michigan's statute specifically provides a 90-day window. Selecting 60 days reflects a common cross-state confusion.

Option C: 180 days

180 days is incorrect. Six months is not the Michigan lien filing deadline. While 180 days may appear in other legal contexts (such as bond claim deadlines on public projects), it is not the standard lien filing window under Act 497.

Option D: 120 days

120 days is incorrect. One hundred twenty days is not the deadline under Michigan's Construction Lien Act. This figure may be confused with other construction-related deadlines or with lien deadlines in other jurisdictions.

Memory Technique

Use the phrase '90 days or no pay.' Once work ends, you have 90 days to record your lien or forfeit your rights in Michigan. Think of it as a 3-month window β€” one full quarter.

Was this explanation helpful?

More Michigan Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.