Under Michigan's Construction Lien Act 497, a subcontractor must serve a Notice of Furnishing within how many days of first furnishing labor or materials?
Correct Answer
B) 20 days
Michigan Construction Lien Act 497 requires subcontractors to serve a Notice of Furnishing within 20 days of first furnishing labor or materials to preserve lien rights.
Why This Is the Correct Answer
Michigan Construction Lien Act 497 requires a subcontractor (or sub-subcontractor, supplier, or laborer who does not have a direct contract with the owner) to serve a Notice of Furnishing within 20 days of first furnishing labor or materials to the project. This preliminary notice is a prerequisite to preserving lien rights — without it, the subcontractor cannot file a valid construction lien.
Why the Other Options Are Wrong
Option A: 10 days
10 days is too short and does not correspond to any Michigan Construction Lien Act deadline. It may be confused with notice requirements under other states' lien laws, but Michigan specifically requires 20 days for the Notice of Furnishing.
Option C: 30 days
30 days is a common distractor because many states use 20–30 day windows for preliminary lien notices. Michigan's specific deadline is 20 days, not 30. Confusing these two numbers is one of the most common exam errors on Michigan lien law.
Option D: 45 days
45 days has no relevance to the Notice of Furnishing deadline. The 45-day period does appear in some contexts in lien law (such as certain notice-to-owner rules in other states), but not for Michigan's Notice of Furnishing requirement.
Memory Technique
20 days = 'Score your notice' (score = 20 in sports like darts). Within 20 days of starting work, score your position with a Notice of Furnishing, or you lose your lien rights.
More Michigan Questions
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
A contractor's employee is injured on a job site in Michigan. The contractor's workers' compensation insurance has a $500 deductible per claim. The total medical costs are $12,500 and lost wages are $3,200. What is the contractor's out-of-pocket cost for this claim?
What is the minimum general liability insurance coverage amount required for Michigan residential builders?
Under Michigan Act 299, what is the consequence for a contractor who performs work outside the scope of their license classification?
A contractor discovers that a subcontractor has filed a construction lien against their project. The general contractor believes the lien is invalid. What is the primary legal mechanism to challenge the lien in Michigan?
Under Michigan Act 299, what happens if a contractor continues to work without a valid license after it expires?
Which of the following best describes the 'pay when paid' clause limitation under Michigan law?
A project has total costs of $180,000 including $75,000 labor and $105,000 materials. With workers compensation at 7.8% of labor costs and general liability at 0.4% of total costs, what are the combined insurance costs?
A Michigan contractor is forming an LLC. What is the minimum general liability insurance coverage required for residential builders under Michigan law?
Under Michigan Act 299, a contractor's license must be renewed every:
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor receives a stop payment notice on a project where they are owed $25,000. Under Michigan lien law, what is the maximum amount the property owner can withhold?
Next Question