Under HRS 507, which of the following parties has priority in a mechanics lien situation?
Correct Answer
C) Labor claims have priority over material claims
Under Hawaii mechanics lien law (HRS 507), claims for labor have priority over claims for materials when multiple liens exist on the same property.
Why This Is the Correct Answer
Hawaii Revised Statutes Chapter 507 (mechanics lien law) explicitly grants priority to labor claims over material claims when multiple liens exist against the same property. This reflects the public policy of protecting workers who personally perform labor before protecting those who supply materials.
Why the Other Options Are Wrong
Option A: The party with the largest claim amount
Lien priority under HRS 507 is not determined by the dollar amount of the claim. A small labor claim can outrank a large material claim. Priority is based on the type of claim (labor vs. material) and sometimes the date of filing, not the size.
Option B: Subcontractors and material suppliers share equal priority
Subcontractors and material suppliers do not share equal priority β HRS 507 creates a hierarchy. Labor claims rank above material claims regardless of whether the claimant is a subcontractor or supplier.
Option D: The general contractor who filed first
Being the general contractor who filed first does not automatically grant priority. Under HRS 507, the type of claim (labor vs. material) determines priority, not the order of filing or the claimant's tier in the construction hierarchy.
Memory Technique
Remember: 'L before M' β Labor before Material in Hawaii mechanics liens. Workers who sweat get paid before suppliers who ship.
More Hawaii Questions
What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?
A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?
A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?
A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?
Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?
A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?
A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?
A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?
A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?
A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?