To achieve LEED Gold certification, a project must earn how many points?

Correct Answer

A) 60-79 points

LEED Gold certification requires 60-79 points. The LEED rating system awards Certified (40-49), Silver (50-59), Gold (60-79), and Platinum (80+) levels based on points earned across various sustainability categories.

Answer Options
A
60-79 points
B
40-49 points
C
50-59 points
D
80-110 points

Why This Is the Correct Answer

LEED Gold certification requires earning between 60-79 points in the LEED rating system. This is the third tier in the four-level LEED certification hierarchy. The Gold level represents a significant commitment to sustainable building practices and environmental performance, requiring substantial points across multiple green building categories including energy efficiency, water conservation, materials selection, and indoor environmental quality.

Why the Other Options Are Wrong

Option B: 40-49 points

80-110 points corresponds to LEED Platinum certification, which is the highest tier above Gold

Option C: 50-59 points

40-49 points corresponds to LEED Certified level, which is the basic entry-level LEED certification, not Gold

Option D: 80-110 points

50-59 points corresponds to LEED Silver certification, which is the second tier below Gold

Memory Technique

Think 'Gold is in the 60s' - Gold certification starts at 60 points, just like how gold is valuable and 60+ represents a substantial achievement in sustainability

Reference Hint

Look up LEED certification requirements in the green building or sustainable construction chapter of your study materials

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.