EstatePass
Contract AdminContractsmedium40% of exam part

In Florida, who must receive a Notice to Owner for lien rights to be preserved?

Correct Answer

C) The owner, general contractor, and lender

Under Florida Statute 713.06, the Notice to Owner must be served on the owner, contractor, and lender (if any) to preserve lien rights. This ensures all key parties are aware of potential lien claimants.

Answer Options
A
Only the property owner
B
The owner and general contractor
C
The owner, general contractor, and lender
D
All parties listed in the Notice to Owner served on the property

Why This Is the Correct Answer

Florida Statute 713.06 specifically requires that the Notice to Owner be served on three key parties: the owner, the general contractor, and the lender (if any) to preserve lien rights. This statutory requirement ensures that all parties with significant financial interest in the project are properly notified of potential lien claimants. Failure to serve any of these required parties can result in the loss of lien rights, making this a critical compliance requirement.

Why the Other Options Are Wrong

Option A: Only the property owner

Option A is incomplete because it only includes the property owner, but Florida law requires notification of additional parties including the general contractor and lender to preserve lien rights.

Option B: The owner and general contractor

Option D is incorrect because it suggests serving all parties listed in the Notice to Owner, but the statute specifically requires only three parties: owner, contractor, and lender (if any), not necessarily all parties that might be mentioned in the notice.

Option D: All parties listed in the Notice to Owner served on the property

Option B is incomplete because while it includes the owner and general contractor, it fails to include the lender, which is also required under Florida Statute 713.06 when a lender is involved in the project.

Memory Technique

Use the acronym 'OCL' (Owner, Contractor, Lender) - think 'Our Construction Liens' to remember the three required recipients of Notice to Owner.

Reference Hint

Florida Building Contractor's Reference Manual - Chapter on Lien Law, specifically Florida Statute 713.06 regarding Notice to Owner requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.