EstatePass
Business & FinanceOperationsmedium10% of exam part

In CPM scheduling, if an activity has an early start of day 10, early finish of day 15, late start of day 14, and late finish of day 19, what is the total float?

Correct Answer

D) 4 days

Total float is calculated as Late Start - Early Start = 14 - 10 = 4 days, or alternatively Late Finish - Early Finish = 19 - 15 = 4 days.

Answer Options
A
9 days
B
0 days
C
5 days
D
4 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project completion date. It is calculated using either Late Start minus Early Start or Late Finish minus Early Finish. Both formulas give the same result because the activity duration remains constant. In this case, 14 - 10 = 4 days and 19 - 15 = 4 days, confirming the total float is 4 days.

Why the Other Options Are Wrong

Option A: 9 days

9 days is incorrect and appears to be a calculation error, possibly adding unrelated numbers or misunderstanding the float formula. This value doesn't correspond to any meaningful CPM calculation for this activity.

Option B: 0 days

0 days would indicate the activity is on the critical path with no scheduling flexibility. However, since there is a 4-day difference between early and late dates, this activity has float and is not critical.

Memory Technique

Remember 'FLOAT = LATE minus EARLY' - you can use either the start dates or finish dates, but always subtract early from late to find how much the activity can 'float' or be delayed.

Reference Hint

Look up CPM (Critical Path Method) scheduling in the project management or scheduling chapter, specifically the section on float calculations and critical path analysis.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.