A general contractor's license expires on March 31st. The contractor submits a renewal application on April 15th. What additional requirement must be met according to Florida Administrative Code 61G4?
Correct Answer
D) Pay late fee and complete additional continuing education
Florida Administrative Code 61G4 requires late renewals to pay additional fees and complete extra continuing education hours. The specific requirements help ensure contractors maintain current knowledge despite late renewal.
Why This Is the Correct Answer
Florida Administrative Code 61G4 requires contractors who submit renewal applications after the March 31st expiration date to meet dual penalties. They must pay additional late fees beyond the standard renewal fee and complete extra continuing education hours (typically 7 additional hours) on top of the regular CE requirements. This dual requirement ensures contractors are penalized for late compliance while still maintaining current professional knowledge.
Why the Other Options Are Wrong
Option B: Complete additional 7 hours of continuing education
While a late fee is required, paying double the renewal fee is not the specific penalty outlined in Florida Administrative Code 61G4. The late fee is a separate additional charge, not a doubling of the base renewal fee, and this option ignores the continuing education requirement.
Option C: Pay double the renewal fee
Retaking the license examination is not required for late renewals within the allowable grace period. This would be an excessive penalty for a late renewal and is typically only required when licenses have been inactive for extended periods or have been revoked.
Memory Technique
Think 'Late = Pay + Learn' - late renewals must PAY extra fees AND LEARN through additional continuing education hours
Reference Hint
Florida Administrative Code 61G4 - License Renewal and Continuing Education Requirements section
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
In CPM scheduling, if an activity has an early start of day 10, early finish of day 15, late start of day 14, and late finish of day 19, what is the total float?
Next Question
Which type of insurance coverage protects against claims that exceed the limits of other primary insurance policies?