EstatePass
Contract AdminProcedureshard13% of exam part

In CPM scheduling, if an activity has a total float of 5 days and free float of 2 days, what happens if this activity is delayed by 3 days?

Correct Answer

D) The next activity will be delayed by 1 day

With 2 days of free float, a 3-day delay will consume the free float and delay the next activity by 1 day (3-2=1). The project completion won't be affected since total float exceeds the delay.

Answer Options
A
The project remains on schedule
B
The project completion date will be delayed by 3 days
C
All subsequent activities will be delayed by 3 days
D
The next activity will be delayed by 1 day

Why This Is the Correct Answer

Free float represents the maximum delay an activity can experience without affecting the start of its immediate successor activities. Since this activity has 2 days of free float and is delayed by 3 days, the free float absorbs 2 days of the delay, leaving 1 day that will push back the start of the next activity. The total float of 5 days is greater than the 3-day delay, so the project's critical path and completion date remain unaffected.

Why the Other Options Are Wrong

Option A: The project remains on schedule

The project schedule is affected because the 3-day delay exceeds the 2-day free float, meaning the next activity will be delayed by 1 day even though the overall project completion remains on schedule.

Option B: The project completion date will be delayed by 3 days

Not all subsequent activities will be delayed by the full 3 days. Only 1 day of delay (3 days minus 2 days of free float) will affect the next activity, and subsequent activities may have their own float to absorb delays.

Option C: All subsequent activities will be delayed by 3 days

The project completion date will not be delayed because the total float (5 days) is greater than the delay (3 days). Total float represents the maximum delay an activity can experience without affecting the project completion date.

Memory Technique

FREE float = affects the NEXT activity FREE of charge. Total float = affects the TOTAL project. Formula: Next Activity Delay = Activity Delay - Free Float (if positive)

Reference Hint

Look up CPM scheduling, float calculations, and activity relationships in the project management or scheduling chapter of your contractor reference manual

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.