In CPM scheduling, if Activity X has an early start of day 10, duration of 5 days, and late finish of day 18, what is the total float for this activity?

Correct Answer

C) 4 days

Early finish = Early start + Duration = 10 + 5 = 15. Total float = Late finish - Early finish = 18 - 15 = 3 days. However, this appears to be a calculation error in the explanation. Let me recalculate: Total float = Late finish - Early finish = 18 - 15 = 3 days, but the late start would be 18 - 5 = 13, so total float = 13 - 10 = 3 days.

Answer Options
A
2 days
B
1 day
C
4 days
D
3 days

Why This Is the Correct Answer

The correct answer is actually C) 3 days, not D) 4 days as stated. Total float represents the amount of time an activity can be delayed without affecting the project completion date. It's calculated as Late Finish - Early Finish, where Early Finish = Early Start + Duration = 10 + 5 = 15 days, and Total Float = 18 - 15 = 3 days. This can also be verified by calculating Late Start - Early Start = (18 - 5) - 10 = 13 - 10 = 3 days.

Why the Other Options Are Wrong

Option A: 2 days

1 day is incorrect because it significantly underestimates the available float time by 2 days

Option D: 3 days

4 days is incorrect because it overestimates the available float time by 1 day, likely from a calculation error

Memory Technique

Remember 'LEAF' - Late minus Early equals Available Float (Late Finish - Early Finish = Total Float)

Reference Hint

Look up CPM scheduling and float calculations in Chapter 6 (Project Management) of the Florida General Contractor Reference Manual

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.