In AIA A201, who typically has the authority to reject work that does not conform to the contract documents?
Correct Answer
A) Both the owner and architect
Under AIA A201, both the owner and architect have authority to reject work that does not conform to the contract documents, though the architect typically acts as the owner's representative in day-to-day administration.
Why This Is the Correct Answer
AIA A201 Section 4.2.6 grants the Architect authority to reject work that does not conform to the contract documents. Additionally, the Owner retains ultimate authority over the project. In practice both parties hold rejection authority, though the Architect exercises it on a day-to-day basis as the Owner's representative.
Why the Other Options Are Wrong
Option B: The general contractor
The General Contractor is responsible for performing conforming work, not for rejecting it. Granting the GC rejection authority would create a conflict of interest β the GC cannot be both the performer and the judge of its own work.
Option C: The architect only
While the Architect does have day-to-day rejection authority under AIA A201 Section 4.2.6, the Owner is not excluded. The Owner retains fundamental contract rights, including the right to reject nonconforming work. Saying 'architect only' is too narrow.
Option D: The owner only
The Owner alone does not exercise day-to-day rejection authority on most projects. The Architect acts as the Owner's representative and is specifically empowered by AIA A201 to reject nonconforming work. Excluding the Architect from this authority misrepresents the contract.
Memory Technique
Remember 'OA can say No' β Owner and Architect together can reject work. The Architect acts first in the field, but the Owner always has standing.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
