For scaffold platforms, what is the maximum allowable gap between planks or between a plank and uprights?
Correct Answer
C) 1 inch
OSHA allows maximum 1-inch gaps between scaffold planks and between planks and uprights to prevent materials or body parts from falling through.
Why This Is the Correct Answer
OSHA's scaffold standard (29 CFR 1926.452) specifies that gaps between scaffold planks and between planks and uprights must not exceed 1 inch. This limitation is critical to prevent tools, materials, or body parts from falling through the platform gaps.
Why the Other Options Are Wrong
Option A: 1/2 inch
1/2 inch is more restrictive than OSHA requires and would make scaffold construction unnecessarily difficult in practice. OSHA sets the maximum at 1 inch, not 1/2 inch.
Option B: 2 inches
2 inches is too large and would create a serious fall-through hazard for smaller tools and potentially fingers or feet. OSHA's 1-inch maximum exists precisely to prevent this level of gap.
Option D: 1-1/4 inches
1-1/4 inches exceeds the OSHA maximum of 1 inch. This option is designed to seem close to correct but would violate the standard.
Memory Technique
One rule, one inch: scaffold plank gaps = 1 inch max. Picture your thumb β it is roughly 1 inch wide. If your thumb fits in the gap, the gap is too big. Close it up.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What is the most important consideration when determining whether to own or rent construction equipment?
Next Question
A concrete slab requires 450 cubic yards of concrete with a water-cement ratio of 0.45. If each bag of cement weighs 94 pounds and the cement content is 564 pounds per cubic yard, how many bags of cement are needed?