For excavation work in Type A soil, a contractor wants to use a simple slope. If the excavation is 10 feet deep, what is the minimum distance from the toe of the slope to the edge of the excavation?

Correct Answer

B) 7.5 feet

Type A soil allows 0.75:1 slope ratio. For 10 feet deep: 10 × 0.75 = 7.5 feet horizontal distance required.

Answer Options
A
20 feet
B
7.5 feet
C
15 feet
D
10 feet

Why This Is the Correct Answer

Cal/OSHA and OSHA 29 CFR 1926 Subpart P classify Type A soil (the most stable) with a maximum allowable slope of 3/4:1 (horizontal:vertical), expressed as a 0.75:1 ratio. For a 10-foot-deep excavation the required horizontal setback is 10 ft × 0.75 = 7.5 feet. This slope ratio reflects Type A soil's cohesive strength and resistance to movement.

Why the Other Options Are Wrong

Option A: 20 feet

20 feet would correspond to a 2:1 slope ratio (10 ft × 2 = 20 ft), which is the requirement for Type C soil — the least stable classification. Using that distance for Type A soil would be overly conservative and incorrect for this calculation.

Option C: 15 feet

15 feet would equal a 1.5:1 ratio, which is the standard for Type B soil. Type B soil is less cohesive than Type A, requiring a shallower, wider slope. Applying Type B requirements to Type A soil overstates the hazard.

Option D: 10 feet

10 feet would be a 1:1 slope (45 degrees). While this might seem intuitive, a 1:1 slope is actually the OSHA requirement for Type B soil in some configurations, not Type A. Type A allows a steeper 0.75:1 cut, meaning you need less horizontal distance.

Memory Technique

Use the ABC mnemonic for soil slope ratios: - Type A = 0.75:1 (three-quarters horizontal per 1 foot of depth) — 'A' for Awesome stability - Type B = 1:1 (one foot horizontal per 1 foot of depth) - Type C = 1.5:1 (one-and-a-half feet horizontal per 1 foot of depth) — 'C' for Crumbly For 10-foot depth: A=7.5 ft, B=10 ft, C=15 ft.

Was this explanation helpful?

More California Questions

A construction site has employees working at heights of 12 feet above the ground on a steep-slope roof. According to Cal/OSHA fall protection requirements, what must be provided?

A construction crew is working outdoors in Fresno when the temperature reaches 97°F. Under Cal/OSHA heat illness prevention requirements, what is the minimum frequency for providing preventive cool-down rest periods?

A contractor is renovating a building built in 1975 and discovers material suspected to contain asbestos. According to Cal/OSHA regulations, what is the first required action?

Under Cal/OSHA regulations, what is the minimum frequency for reviewing and updating an Injury and Illness Prevention Program (IIPP)?

Calculate the minimum shade area required for 8 construction workers during a heat illness prevention cool-down period in California:

An employee working with lead-based paint removal has a blood lead level of 45 μg/dl. According to Cal/OSHA lead standards, what action must the employer take?

An IIPP must include procedures for investigating workplace accidents. According to Cal/OSHA, who is responsible for conducting these investigations?

A competent person inspecting a trench notices water seepage and minor soil movement. Under Cal/OSHA excavation standards, what action is required?

Calculate the required air changes per hour for a confined space with lead work under Cal/OSHA regulations. The space volume is 1,200 cubic feet and the exhaust fan moves 400 CFM. How many air changes per hour are being provided?

A roofing contractor is installing fall protection on a commercial building. Under Cal/OSHA Title 8, Section 1710, at what height does fall protection become mandatory for construction work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.