EstatePass
Contract AdminContractsmedium40% of exam part

During project closeout, the owner identifies minor deficiencies that do not affect the substantial use of the building. The contractor argues these items should not delay substantial completion. Who typically makes the final determination?

Correct Answer

C) The architect/engineer

Under typical AIA contracts, the architect or engineer makes the determination of substantial completion. They assess whether the work is sufficiently complete for the owner's intended use, even with minor deficiencies that can be addressed in a punch list.

Answer Options
A
The contractor
B
The owner
C
The architect/engineer
D
A third-party inspector

Why This Is the Correct Answer

CORRECT_ANSWER - Under standard AIA contracts and most construction agreements, the architect or engineer serves as the neutral professional who determines substantial completion. They have the technical expertise to assess whether the work is sufficiently complete for the owner's intended use, even with minor deficiencies present. The architect/engineer evaluates the project objectively and creates the punch list for remaining items that don't prevent occupancy or use.

Why the Other Options Are Wrong

Option A: The contractor

Third-party inspectors are typically brought in for specific technical evaluations or dispute resolution, but the standard contract framework designates the architect/engineer as the primary decision-maker for substantial completion determinations.

Option D: A third-party inspector

While the owner has the ultimate say in accepting the project, they typically lack the technical expertise to determine what constitutes substantial completion versus final completion. Owners may also be overly critical of minor deficiencies that don't actually impact the building's intended use.

Memory Technique

Think 'A for Architect = Arbiter' - the architect serves as the neutral arbiter for completion decisions between owner and contractor.

Reference Hint

AIA Contract Documents - specifically AIA A201 General Conditions, Section on Substantial Completion and Certificate of Substantial Completion

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.