EstatePass
Contract AdminContractsmedium40% of exam part

During final closeout, the architect identifies $12,000 worth of punch list items. The contract retainage held is $45,000. The owner wants to release $30,000 of retainage and hold $15,000 pending completion of punch list work. Is this approach reasonable?

Correct Answer

A) Yes, this provides reasonable security while releasing most funds

Holding $15,000 against $12,000 of punch list work provides reasonable security for the owner while releasing the majority of retainage funds. This approach balances the owner's protection with the contractor's cash flow needs.

Answer Options
A
Yes, this provides reasonable security while releasing most funds
B
Yes, but only if the contractor agrees in writing
C
No, retainage can only be released after final completion
D
No, all retainage must be held until punch list completion

Why This Is the Correct Answer

CORRECT_ANSWER - This approach is reasonable because it provides adequate security for the owner while improving the contractor's cash flow. Holding $15,000 against $12,000 of punch list work gives the owner a 125% security margin, which is more than sufficient to cover the remaining work. The practice of partial retainage release during closeout is common and beneficial when properly managed with appropriate security ratios.

Why the Other Options Are Wrong

Option B: Yes, but only if the contractor agrees in writing

While retainage is typically held until final completion, partial release during closeout is acceptable when sufficient security remains. This rigid interpretation doesn't account for reasonable business practices that balance owner protection with contractor cash flow needs.

Option D: No, all retainage must be held until punch list completion

While contractor agreement is always preferable, it's not legally required for the owner to make this reasonable adjustment to retainage release. The owner has the right to manage retainage releases as long as they maintain adequate security for remaining work.

Memory Technique

Remember 'R.S.R.' - Reasonable Security Ratio. As long as retainage held exceeds remaining work value by 10-50%, partial release is typically acceptable.

Reference Hint

Florida Building Code Chapter 1, Section 713 (Lien Law) and AIA A201 General Conditions regarding retainage and substantial completion procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.