EstatePass
Contract AdminPreconstructionhard27% of exam part

A framing crew's productivity decreases from 1,000 board feet per day to 750 board feet per day when working in cold weather. If the crew cost is $2,400 per day, what is the increased labor cost per board foot due to weather?

Correct Answer

D) $0.80

Normal cost: $2,400 ÷ 1,000 = $2.40 per board foot. Cold weather cost: $2,400 ÷ 750 = $3.20 per board foot. Increased cost: $3.20 - $2.40 = $0.80 per board foot.

Answer Options
A
$0.60
B
$3.20
C
$1.20
D
$0.80

Why This Is the Correct Answer

Option B is correct because it properly calculates the difference in labor cost per board foot between normal and cold weather conditions. The calculation involves finding the cost per board foot under normal conditions ($2.40), then under cold weather conditions ($3.20), and subtracting to find the increased cost ($0.80). This represents the additional cost burden imposed by the reduced productivity in cold weather.

Why the Other Options Are Wrong

Option A: $0.60

$0.60 is incorrect because it underestimates the increased cost. This might result from calculation errors or using incorrect productivity figures.

Option B: $3.20

$1.20 is incorrect because it overestimates the increased cost. This could result from miscalculating the difference or confusing the calculation steps.

Memory Technique

Remember 'PCD' - Productivity Change = Difference. When productivity goes down, cost per unit goes up. Always subtract the original rate from the new rate to find the increase.

Reference Hint

Look up productivity factors and weather impacts in construction estimating chapters, typically found in cost control or scheduling sections of contractor reference materials.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.