EstatePass
Contract AdminPreconstructionhard27% of exam part

A contractor needs 15,000 board feet of lumber. The supplier quotes $4.25 per board foot with a 5% discount for orders over 10,000 board feet and 2% additional discount for payment within 10 days. What is the total cost if both discounts apply?

Correct Answer

B) $59,456.25

Base cost: 15,000 × $4.25 = $63,750. After 5% discount: $63,750 × 0.95 = $60,562.50. After additional 2% discount: $60,562.50 × 0.98 = $59,456.25.

Answer Options
A
$60,562.50
B
$59,456.25
C
$63,750.00
D
$58,537.50

Why This Is the Correct Answer

The correct answer applies both discounts sequentially to the base cost. First, the 5% volume discount is applied to the original amount, then the 2% early payment discount is applied to the already-discounted amount. This compound discount calculation results in a total cost of $59,456.25, which represents the maximum savings available to the contractor.

Why the Other Options Are Wrong

Option A: $60,562.50

This amount represents the cost after only applying the first 5% volume discount ($60,562.50) but fails to apply the additional 2% early payment discount that the contractor qualifies for.

Option C: $63,750.00

This is the base cost before any discounts are applied ($63,750), ignoring both the 5% volume discount and the 2% early payment discount that the contractor qualifies for.

Option D: $58,537.50

This amount appears to incorrectly calculate the discounts, possibly by adding the percentages together (7%) rather than applying them sequentially, or by making an arithmetic error in the calculation process.

Memory Technique

Remember 'Sequential Savings' - discounts stack on top of each other, so always multiply by the remaining percentage (95% then 98%) rather than subtracting the full percentages from 100%.

Reference Hint

Florida Building Construction Standards and Practices - Chapter on Cost Estimation and Material Calculations, or Business and Finance section covering discount calculations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.