EstatePass
Contract AdminContractshard40% of exam part

During contract closeout, the contractor discovers that one of the required warranties was not obtained from a subcontractor. The owner is demanding occupancy next week. What is the most appropriate action?

Correct Answer

D) Provide financial assurance for the missing warranty and complete closeout

The most professional approach is to provide financial assurance (such as a bond or escrow) for the missing warranty while completing the closeout process. This protects the owner while allowing occupancy and final completion.

Answer Options
A
Withhold final payment until warranty is provided
B
Proceed with closeout and obtain warranty later
C
Negotiate with owner to accept contractor warranty in lieu of subcontractor warranty
D
Provide financial assurance for the missing warranty and complete closeout

Why This Is the Correct Answer

Option D provides the most balanced solution that protects all parties' interests. Financial assurance (bond or escrow) guarantees the owner will be covered for the missing warranty while allowing the project to close out on schedule. This approach maintains professional relationships, meets contractual obligations, and provides a concrete remedy rather than just promises. It demonstrates proper risk management and allows the owner to take occupancy as needed.

Why the Other Options Are Wrong

Option A: Withhold final payment until warranty is provided

This option exposes the owner to unacceptable risk and violates contractual obligations. Proceeding without proper warranty protection leaves the owner vulnerable if defects occur, and obtaining warranties 'later' provides no guarantee or timeline. This approach could result in legal liability for the contractor and damages the professional relationship.

Option B: Proceed with closeout and obtain warranty later

While withholding payment creates leverage, it doesn't solve the immediate problem of the owner needing occupancy next week. This approach could delay the entire project closeout indefinitely and may breach the contractor's obligation to deliver the project on time. It also doesn't provide the owner with any warranty protection in the interim.

Memory Technique

Think 'FAIR' - Financial Assurance Insures Responsibility. When warranties are missing, financial backing ensures everyone's protected while the project moves forward.

Reference Hint

Florida Building Code Chapter 1, Section 110 - Certificate of Occupancy requirements and contract closeout procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.