EstatePass
NASCLAContractshard15% of exam part

During construction, the owner requests additional work valued at $125,000. The architect issues a change directive, but the contractor disputes the amount. Under typical AIA contract terms, how should the contractor proceed?

Correct Answer

C) Perform the work and continue to negotiate the price

Under AIA contracts, a change directive requires the contractor to proceed with the work while price negotiations continue, ensuring project progress.

Answer Options
A
Refuse to perform the work until a change order is signed
B
Stop all work on the project until the dispute is resolved
C
Perform the work and continue to negotiate the price
D
Demand immediate arbitration before proceeding

Why This Is the Correct Answer

Under AIA contracts, a change directive requires the contractor to proceed with the work while price negotiations continue, ensuring project progress.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.