During construction, the owner requests additional work valued at $125,000. The architect issues a change directive, but the contractor disputes the amount. Under typical AIA contract terms, how should the contractor proceed?
Correct Answer
C) Perform the work and continue to negotiate the price
Under AIA contracts, a change directive requires the contractor to proceed with the work while price negotiations continue, ensuring project progress.
Why This Is the Correct Answer
Under AIA contracts, a change directive requires the contractor to proceed with the work while price negotiations continue, ensuring project progress.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A worker is using a pneumatic nail gun on a construction site. The noise level at the worker's ear is measured at 95 dBA for an 8-hour shift. What hearing protection is required?
Next Question
Which mortar type is most appropriate for exterior walls below grade that will be subject to high lateral earth pressure?
