During construction, a utility line is discovered 3 feet from its location shown on the drawings. The contractor relocates the line and continues work. What documentation is required?

Correct Answer

A) Updated as-built drawings showing the actual utility location

The actual utility location must be documented in the as-built drawings to provide accurate information for future work. This prevents conflicts and safety hazards in future projects.

Answer Options
A
Updated as-built drawings showing the actual utility location
B
A change order only
C
No documentation since the issue was resolved
D
A field report noting the discovery

Why This Is the Correct Answer

As-built drawings are legal documents that must accurately reflect the actual constructed conditions, not just the original design. When utilities are discovered in different locations than shown on the original drawings, this critical information must be documented in the as-built drawings to ensure future safety and prevent conflicts during renovations, expansions, or other construction work. This documentation protects future contractors, engineers, and workers who will rely on these drawings for accurate utility locations. Failure to update as-built drawings with actual utility locations can result in serious safety hazards, legal liability, and costly damages in future projects.

Why the Other Options Are Wrong

Option C: No documentation since the issue was resolved

While a change order may be needed for cost adjustments related to relocating the utility, it alone is insufficient documentation. Change orders primarily address contractual and financial aspects, but don't serve as permanent record drawings that future contractors will reference for utility locations.

Option D: A field report noting the discovery

A field report is temporary documentation that notes the discovery but doesn't provide the permanent, accurate record needed for future reference. Field reports are typically internal documents and don't become part of the permanent project record that future contractors will use.

Memory Technique

Think 'AS-BUILT = AS-ACTUALLY-BUILT' - these drawings must show reality, not the original plan. When utilities move, the as-builts must move with them.

Reference Hint

Florida Building Code, Chapter 1, Administration and Enforcement - Documentation Requirements; also check contract administration sections regarding as-built drawing requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.