EstatePass
Contract AdminProceduresmedium13% of exam part

During a weekly construction coordination meeting, the electrical subcontractor reports they are 3 days behind schedule on a non-critical path activity with 5 days of total float. What should the general contractor's immediate response be?

Correct Answer

C) Document the delay and continue monitoring since float remains available

Since the activity has 5 days of total float and is only 3 days behind, there is still 2 days of float remaining. The delay does not impact the critical path, so documentation and continued monitoring is appropriate.

Answer Options
A
Notify the owner of a project delay
B
Immediately accelerate the electrical work at additional cost
C
Document the delay and continue monitoring since float remains available
D
Terminate the electrical subcontractor for poor performance

Why This Is the Correct Answer

Option B is correct because the activity still has remaining float (5 days total float - 3 days delay = 2 days remaining). Since this is a non-critical path activity with available float, the delay does not impact the overall project schedule. The appropriate response is to document the delay for tracking purposes and continue monitoring the situation, as no immediate corrective action is required when float remains available.

Why the Other Options Are Wrong

Option A: Notify the owner of a project delay

Notifying the owner of a project delay would be inappropriate since there is no actual project delay. The activity delay is absorbed by the available float, so the overall project schedule remains unchanged.

Option D: Terminate the electrical subcontractor for poor performance

Terminating a subcontractor for a 3-day delay on a non-critical activity with available float would be an extreme overreaction. This delay doesn't constitute poor performance warranting termination, especially when it doesn't impact the project completion date.

Memory Technique

Use 'FLOAT = FREEDOM': As long as you have float remaining, you have the freedom to absorb delays without impacting the project completion date.

Reference Hint

Project Management/CPM Scheduling chapter - look for sections on 'Float' or 'Total Float' and 'Critical Path Method'

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.