During a pre-construction meeting, the electrical subcontractor requests to start rough-in work before the framing is complete. As the general contractor, what is the most appropriate response?

Correct Answer

D) Deny the request and refer to the project schedule dependencies

Electrical rough-in typically depends on framing completion for proper installation. The GC should maintain schedule logic and safety by following proper sequencing.

Answer Options
A
Approve only if the electrical contractor assumes liability
B
Approve the request to accelerate the schedule
C
Require written approval from the owner first
D
Deny the request and refer to the project schedule dependencies

Why This Is the Correct Answer

Electrical rough-in typically depends on framing completion for proper installation. The GC should maintain schedule logic and safety by following proper sequencing.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.