EstatePass
CaliforniaTrademedium20% of exam part

During a building inspection, you discover that the contractor used 2x4 studs at 24 inches on center for an exterior bearing wall in a two-story residence. According to CBC, what is the verdict?

Correct Answer

B) Acceptable for second story only

CBC allows 2x4 studs at 24 inches on center for the second story of a two-story building, but the first story bearing wall requires 2x6 studs or 2x4 studs at 16 inches on center due to increased load.

Answer Options
A
Acceptable for first story only
B
Acceptable for second story only
C
Not acceptable for either story
D
Acceptable for both stories

Why This Is the Correct Answer

CBC permits 2x4 studs at 24 inches on center in the second story of a two-story bearing wall because the load above is limited to the roof and second-floor structure. The first story, however, carries the additional weight of the second story, roof, and all live loads, requiring greater capacity — either 2x6 studs or 2x4s at a closer 16-inch spacing.

Why the Other Options Are Wrong

Option A: Acceptable for first story only

2x4 at 24 inches on center is not acceptable for the first story, which bears the full cumulative structural load. The first floor requires 2x6 studs or 2x4s at 16 inches OC to handle the increased demand.

Option C: Not acceptable for either story

'Not acceptable for either story' overstates the restriction. The code specifically permits this lighter framing configuration for the second (upper) story where loads are lower.

Option D: Acceptable for both stories

'Acceptable for both stories' is wrong because the first story has higher loads requiring heavier framing. Allowing 2x4 at 24 OC throughout both stories would violate CBC for the lower story.

Memory Technique

Second story = lighter load = lighter framing allowed. Think: 'Top gets 24, bottom needs more.' The second story is on top — it carries less — so the looser 24-inch spacing is permitted there.

Was this explanation helpful?

More California Questions

A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?

You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?

According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?

A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?

You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?

A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?

During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?

During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?

What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?

You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.