Calculate the workers compensation premium for a South Carolina roofing contractor with $250,000 in annual payroll. The rate classification is 5551 with a rate of $28.50 per $100 of payroll.
Correct Answer
A) $71,250
Workers comp premium = ($250,000 ÷ $100) × $28.50 = 2,500 × $28.50 = $71,250
Why This Is the Correct Answer
The formula for workers' compensation premium is: (Payroll ÷ 100) × Rate. Applying the numbers: ($250,000 ÷ 100) × $28.50 = 2,500 × $28.50 = $71,250. This is a straightforward application of the standard premium calculation formula used across the insurance industry.
Why the Other Options Are Wrong
Option B: $78,500
$78,500 does not result from the correct formula. It may result from an arithmetic error such as using a wrong divisor or multiplying by an incorrect rate. Always verify by working the formula step by step: divide payroll by 100 first, then multiply by the rate.
Option C: $75,000
$75,000 is close but incorrect. It might result from rounding $28.50 up to $30 ($250,000 ÷ 100 × $30 = $75,000) or some other rounding error. The exam requires precise calculation — do not round intermediate values.
Option D: $68,250
$68,250 does not result from correct application of the formula. It could stem from using a lower rate or making a subtraction error. Verify each arithmetic step carefully: $250,000 ÷ 100 = 2,500; then 2,500 × $28.50 = $71,250.
Memory Technique
The rate is always expressed 'per $100 of payroll,' so you must convert payroll into units of $100. Think of it as: how many $100 chunks are in your payroll? ($250,000 ÷ $100 = 2,500 chunks). Then multiply: 2,500 chunks × $28.50 per chunk = $71,250. Roofing has a very high rate (around $28-30 per $100) because it is one of the most hazardous classifications.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?